Organization Project Name Capacity Unit Fixed capital  (M €) Working capital (M €) Total investment (M €)   Payback Period (year)
Ministry of Energy Desalination plant 3000 m3/day 2.33 0.28 2.61 21% 5.6
Ministry of Energy Desalination plant 750 m3/day 0.59 0.09 0.68 18% 6.4
Ministry of Energy Desalination plant 250 m3/day 0.20 0.04 0.24 14% 7.8
Ministry of Energy Desalination plant 400 m3/day 0.31 0.05 0.36 17% 6.7
Ministry of Energy Desalination plant 2000 m3/day 1.51 0.19 1.70 22% 5.5
Ministry of Energy Photovoltaic power station 10.00 MW 16.09 1.53 17.62 24% 7.4
Ministry of Energy Photovoltaic power station 5.00 MW 8.05 0.76 8.81 24% 7.4
Ministry of Energy water distribution system- tiss     1.04 0.01 1.05 17% 10.0
Ministry of Energy water distribution system- bris     3.34 0.04 3.38 18% 10.0
Ministry of Energy water distribution system- pishin     79.21 1.34 80.55 20% 6.0